1. Introduktion

This manual provides essential instructions for the installation, operation, and maintenance of the BFT SB-BAT P125002 24V DC Battery Backup Kit. This kit is designed to ensure continuous operation of compatible BFT gate openers during temporary power outages. Please read this manual thoroughly before proceeding with installation or use.

2. Produktet er slutview

The BFT SB-BAT P125002 is a 24V DC battery backup system that integrates with specific BFT gate operators. It includes a smart charger board that manages battery charging when main power is available and automatically switches to battery power when the main supply is interrupted.

BFT SB-BAT P125002 Battery Backup Kit components in box

Figur 1: Overview of the BFT SB-BAT P125002 Battery Backup Kit, showing the product box, two batteries, wiring, and mounting hardware.

2.1. Kitkomponenter

Individual components of the BFT SB-BAT P125002 Battery Backup Kit

Figur 2: Detaljeret view of the BFT SB-BAT P125002 kit components, including batteries, wiring, mounting brackets, and the battery holder.

3. Kompatibilitet

This battery backup system is compatible with the following BFT gate operator series:

Ensure your gate operator model is listed above for proper functionality.

4. Opsætning og installation

Installation of the BFT SB-BAT P125002 kit is designed to be straightforward. However, it is recommended that installation be performed by a qualified technician to ensure safety and correct operation. Always disconnect main power to the gate operator before beginning installation.

4.1. Sikkerhedsforanstaltninger

4.2. Installationstrin (generelle retningslinjer)

  1. Mount the Battery Holder: Secure the battery holder/mounting base within the gate operator's control box or an appropriate enclosure using the provided mounting brackets and fasteners. Ensure it is stable and accessible.
  2. Indsæt batterier: Place the two 12V 1.2Ah batteries into the battery holder.
  3. Tilslut batterier: Connect the batteries in series to achieve 24V DC, following the wiring diagram provided with your specific gate operator or the kit's smart charger board. Ensure correct polarity.
  4. Connect Smart Charger Board: Integrate the smart charger board into the gate operator's control unit. Refer to your gate operator's manual for the specific connection points for the battery backup system.
  5. Sikker ledningsføring: Route and secure all wiring to prevent pinching or damage.
  6. Gendan strøm: Once all connections are verified and secure, restore main power to the gate operator. The smart charger board will begin charging the batteries.
  7. Test system: Perform a power outage simulation to verify the battery backup system activates correctly and powers the gate operator.

5. Betjeningsvejledning

The BFT SB-BAT P125002 operates automatically once installed correctly.

5.1. Normal Operation (Power On)

When main power is supplied to the gate operator, the smart charger board within the SB-BAT kit continuously monitors the battery charge level. It will charge the batteries as needed to maintain them at full capacity.

5.2. Power Outage Operation (Power Off)

I tilfælde af en magt outage, the smart charger board automatically detects the loss of main power and switches the gate operator to battery power. The gate operator will then function normally using the stored energy in the batteries. The duration of operation on battery power depends on the frequency of gate usage and the charge level of the batteries.

6. Vedligeholdelse

Regular maintenance ensures the longevity and reliability of your battery backup system.

6.1. Batteriopladning

Efter en magt outage, once main power is restored, the smart charger board will automatically begin recharging the batteries. A full recharge typically takes 12 til 14 timer. It is important to allow sufficient time for batteries to fully recharge after use.

6.2. Fuse Check

Systemet indeholder en 20A sikring for protection. If the battery backup system fails to operate or charge, inspect the fuse for continuity. Replace with a fuse of the exact same rating if necessary. Always disconnect power before checking or replacing fuses.

6.3. Batterilevetid og udskiftning

Batteries have a finite lifespan. Periodically test the system by simulating a power outage to ensure batteries hold a charge and can power the gate operator. If performance degrades significantly, consider replacing the batteries. Use only recommended replacement batteries (2x 12V 1.2Ah sealed lead-acid).

7. Fejlfinding

If your BFT SB-BAT P125002 battery backup system is not functioning as expected, consider the following:

For persistent issues, contact BFT technical support or a qualified service technician.

8. Specifikationer

FeatureSpecifikation
ModelnummerP125002
BatteritypeForseglet bly-syre
Batterikapacitet2x (12V 1.2Ah)
Udgang Voltage24V DC (nominel)
Charge Voltage27.2V
Ladestrøm130mA
Batteriopladningstid12-14 timer
Exhausted Battery Protection Threshold20.4V
Sikringsvurdering20A
DriftstemperaturData detected with external temperature of: 25°C (77°F)

9. Garanti og support

For warranty information, please refer to the documentation provided with your original purchase or contact BFT customer support directly. For technical assistance, installation queries, or troubleshooting beyond the scope of this manual, please contact your authorized BFT dealer or BFT technical support.

BFT Contact Information: Please visit the official BFT webwebstedet for de seneste kontaktoplysninger og supportressourcer.

Relaterede dokumenter - P125002

Preview BFT DEIMOS BT UL/CSA Elektromekanisk Portautomationssystem
Discover the BFT DEIMOS BT UL/CSA, an electromechanical automation system for rack sliding gates. Featuring smart technology, 24V safe operation, and simplified installation, this system enhances gate security and convenience. Explore its technical specifications and available accessories for residential and commercial applications.
Preview BFT Mitto 2M/4M fjernkodningsvejledning: En omfattende guide
Lær, hvordan du programmerer dine BFT Mitto 2M og 4M fjernbetjeninger til garage- og portåbnere. Denne vejledning dækker kodning af modtagere med og uden digitale skærme, inklusive vigtige sikkerhedsadvarsler.
Preview BFT VIRGO Installationsmanual til automatisering af svingporte
Omfattende installations- og brugervejledning til BFT VIRGO svingportsautomationssystem, der dækker sikkerhed, tekniske specifikationer, installationsprocedurer, programmering og vedligeholdelse.
Preview Vejledning til installation og brug BFT GIOTTO 30-60 S BT / GIOTTO 30-60 BT
Komplet vejledning til installation og brug af automatiske barriere BFT GIOTTO 30-60 S BT og GIOTTO 30-60 BT. Inkluder specifik teknik, konfiguration og betjening.
Preview Instruktioner til kodning af BFT MITTO 2B fjernbetjening | Retro fjernbetjeninger
Trin-for-trin-vejledning til kodning af BFT MITTO 2B fjernbetjeninger til portåbnere, der dækker eksisterende fjernbetjenings- og modtager-LCD-skærmmetoder. Indeholder fejlfindingstips.
Preview Installationsvejledning til BFT CLONIX1-2 & MITTO 2-4 433MHz radiostyringssystem
Omfattende installationsvejledning til BFT CLONIX1-2-modtageren og MITTO 2-4 433MHz radiostyringssendere, der dækker programmering, kloning, sikkerhed og tekniske specifikationer for port- og dørautomation.